City map shows street to be resurfaced in spring

The dark lines on this map show the areas of Curtis Park to be resurfaced in spring 2018. The tentative schedule is for construction from April through June. Streets will get what is called a cape seal resurfacing, which is a two-part process. The first step is a chip seal, a layer of rock placed in an asphalt emulsion, which gives the appearance of a gravel road. Seven to 14 days later, a final layer of slurry seal will be placed. Information will be posted on the city’s website at www. cityofsacramento.org. The city says informational flyers will be mailed to all residents before the project begins, and door hangers will be placed at every residence indicating the date of roadwork.

Written by Viewpoint Staff and posted on Friday, February 23rd, 2018